This project involved a multi-utility infrastructure package, elevator pit and interior footings for a new, multi-purpose arena addition at Lavietes Pavilion. Demolition work included removal of the side walk trench drains, as well as the existing sewer, water and electrical lines. New water services, hydrant and water gates were installed and connected to the existing water main. The team maintained strict protection of 20 trees, 2 light poles and numerous blue lights on campus.